By the technical team at Construction & Electrical Products Inc. · Pompano Beach, Florida
Epoxy anchors for brick and block go wrong in a way that concrete never teaches you. The hole is drilled, the resin goes in, and it disappears into a hollow core nobody knew was there, leaving a rod held by a fraction of what the crew pumped in. Nothing looks wrong from the face of the wall. The real question is not which epoxy to use. It is what the wall is made of, and whether the product was qualified for it.
The rule is simple: identify the masonry before you pick the anchor, use a screen tube wherever the instructions call for one in hollow units, and use only a product whose evaluation report covers masonry, because a report written for concrete does not carry over. On a real job, epoxy anchors for brick and block hold signs, handrails, equipment frames, door hardware and conduit supports on walls of solid brick, hollow concrete block and grout-filled block. The resin holds them by filling the hole and bonding to the unit, and in a hollow unit by filling a mesh tube set in the void.
What Epoxy Anchors for Brick and Block Are Set In
Masonry is not one material. Solid brick, hollow CMU, grout-filled block, natural stone and damaged historic walls all behave differently, so you do not start with an anchor choice, you start with verification.
A concrete masonry unit is a block with cores. ASTM C90 covers loadbearing concrete masonry units, both hollow and solid. In a hollow unit the cores are separated by webs and closed at the face by a face shell, and the thickness of that shell is what an anchor has to work with. A grout-filled cell is a core that was filled solid, sometimes with a bar in it. Solid brick has no cores at all. A wall can be any of these, or a mix of them, and the face does not say which.
Why Concrete Rules Do Not Carry Over
A resin is qualified for a base material, and the base material is on the report. ICC-ES AC308 covers post-installed adhesive anchors and reinforcing bars in concrete. AC58 is a separate criteria document, titled Adhesive Anchors in Cracked and Uncracked Masonry Elements. Two documents, two substrates. A product listed for concrete has no standing in a block wall, and the reverse is also true.
Design follows the same split. The masonry design and construction standard is TMS 402/602-22, which covers structural design and minimum construction requirements for masonry. Embedment, spacing, edge distance and capacity in a masonry wall belong to the engineer of record, working from the evaluation report. If the base material is wrong, every other decision is secondary.
What a Screen Tube Does
In a hollow unit, injected resin has somewhere to go, and it goes there. A screen tube is a perforated or mesh sleeve set in the hole. The resin fills the tube, pushes through the mesh and bonds to the surrounding material, and the rod sits in a column of resin instead of an open core. Without the tube, the resin flows into the void and stays there.
Whether a tube is required, how long it must be, what diameter it must have and how much resin fills it are written in the instructions for the product, and the tube is part of the system the report covers. A tube from one product is not a substitute for a tube from another. Resin that vanishes and never comes back to the face is the field signal for a core with no tube.
What Decides Which Product You Can Use
Three things settle it. The first is the base material and its condition, because the report lists the masonry it was qualified for. The second is how the hole is made. The instructions say whether hollow units are drilled with hammer action or in rotation only, since hammer action can break out a thin face shell. The third is where the hole sits: near the end of a wall, near a corner, or near a mortar joint, which is a design question with an answer on the drawings, not in the field.
For solid and filled units, the same reading applies, with a different set of conditions. A product qualified for hollow units and one qualified for solid units can be two different listings. Read the one that matches the wall.
Reading the Wall Before You Drill
Maintenance work happens on walls nobody drew. There is no drawing for a wall built decades ago and patched twice, so read it. Tap the wall and listen for the change from solid to hollow. Look at the joints, because cracked mortar joints, spalled brick and patched penetrations change the failure mode immediately. Watch the bit: a drill that drops suddenly has reached a void, and a change in dust color tells you the same thing.
A trial hole in an out-of-the-way spot answers a lot of questions, but it can also reach a bar in a grouted cell, so stop if the bit rings against steel. If the wall is structural or its construction is unknown, take the question to the engineer of record before the cartridge is opened. Keep the instructions and the evaluation report with the anchor record, so the next person on that wall starts with what you learned. For a maintenance team, the habit worth building is a wall log: which wall, which type of unit it turned out to be, which product and report were used, and where the anchors went. A wall that was read once does not have to be read again, and the next work order starts with an answer instead of a guess.
Corrosion and Environment
A rod in an exterior wall is exposed at the face, and in a hollow wall it can sit in a cavity that stays damp. Salt in the air reaches the exposed end first, and moisture inside the wall can keep working on the part nobody sees. The finish of the rod is a purchasing decision made before the drill comes out, and 316 stainless fasteners for coastal Florida goes through why the grade matters near the coast. Commercial buyers who ignore environment always pay twice.
Which steel element goes in the resin is the next question. The report lists the rods and bars it was qualified with for masonry, and the difference between them is covered in threaded rod vs rebar dowel.
Documentation and Code Path
Three documents travel with an epoxy anchor in masonry: the specification, the manufacturer’s instructions for the exact product and the evaluation report that lists the masonry. Whether an anchor into a particular wall needs engineering review, special inspection or a permit is for the specification and the building official to say. Do not assume the answer from the size of the job.
Mechanical anchors are the other path into masonry, covered in masonry anchors, commercial masonry anchors and, for installation, masonry anchor installation. Construction & Electrical Products Inc. lists its epoxy anchoring systems under a catalog category named for masonry and hammer capsules, and the hammer anchoring capsules page is the place to start for that product.
Solid Units, Filled Cells and Hollow Units
Solid brick and grout-filled block
These behave most like a solid base, but they are not concrete. The report must list the masonry, and the instructions say how to drill it and where in the unit the anchor can go.
Hollow block
Here the screen tube is usually the difference between an anchor and a hole full of resin. The face shell and the tube do the work together, and the thickness of the shell limits what the wall can hold.
What decides it
The wall decides it, and the report confirms it. If you cannot say which of the three you are drilling, you are not ready to open the cartridge.
Mistakes Made With Good Intentions
Each of these comes from someone trying to get a sign or a rail up before the end of the shift. A concrete-rated resin gets used because the cartridge is in the truck, and the report never covered masonry. The tube gets skipped because the resin will surely find the face shell, and it finds the core. Resin is pumped until it shows at the face to be sure, and the core swallows it. The bit goes through the far face shell because the hole was drilled to the bottom of the unit, not to the embedment. A hole gets drilled in the mortar joint because the drill goes in easily, and the joint was not what the product was qualified for. The drill is left in hammer mode through a thin face shell, and the shell breaks.
Assume a wall has 40 anchor points and one in four opens into a void nobody drew. That is ten holes that need a different approach and ten cartridges’ worth of resin that went into the wall. The saving from skipping the check is never larger than the cost of that one.
What to Confirm Before You Drill
Check the masonry type, its condition, the evaluation report, the tube requirement and the drilling mode. If one of those five is not clear, do not drill. Before the first hole, confirm:
- The wall is identified as solid brick, filled block or hollow block.
- The evaluation report for the exact product covers masonry, not only concrete.
- The instructions say whether a screen tube is needed, and the tube is the one for the product.
- The drilling mode matches the instructions for that unit.
- The hole location is clear of edges, corners and joints the drawing restricts.
- The steel element and its finish are ones the report lists, and the finish suits the exposure.
- The instructions and the report are on site and filed with the anchor record.
The whole sequence from drilling to the record is in epoxy anchor installation, and the documents the manufacturer posts are in the technical section.
Frequently Asked Questions
Can you use epoxy anchors in brick?
Yes, with a product whose instructions and evaluation report cover masonry, and after the condition of the brick is checked.
Can you use epoxy anchors in hollow block?
Yes, when the product is qualified for hollow units. That usually means a screen tube, and the instructions say so.
What is a screen tube for an epoxy anchor?
It is a perforated or mesh sleeve set in the hole so that resin fills the tube instead of flowing into the open core. It is part of the system the report covers.
Can you use an epoxy rated for concrete in a block wall?
Not unless the evaluation report also covers masonry. Concrete and masonry are separate listings.
Should you hammer drill brick and block?
The instructions for the product say. Hammer action can break out a thin face shell, so follow the drilling mode the manufacturer gives.
Who decides embedment and spacing in masonry?
The engineer of record decides, using the evaluation report and the masonry design standard that applies to the project.
About Construction & Electrical Products Inc. Construction & Electrical Products Inc. is an independent distributor of construction, electrical, safety and industrial supplies based in Pompano Beach, Florida, with more than 50 years in the trade and more than 10,000 products in stock, including anchors, fasteners, drill bits, diamond products, saw blades, epoxy anchoring systems, cable ties, wire connectors, terminals, GFCI devices and emergency lighting. Orders ship with no minimum, drop shipment to the job site is available, and Certificates of Compliance and Mill Test Reports are provided on request. Read more about the company and browse the manufacturer documents in the technical section.
This article is general product and procurement information. It is not an engineering opinion, a design recommendation, or a substitute for the project specification. Anchor selection, embedment, spacing, edge distance and design capacity are determined by the engineer of record for the specific project, and the governing values are those published in the manufacturer’s current evaluation report and installation instructions for the exact part number. Construction & Electrical Products Inc. supplies products and manufacturer documentation. It does not design anchorage or perform engineering services.
The installation steps described here are general and may not apply to the product on your job. Always follow the manufacturer’s current printed instructions for the specific part number, diameter and base material, and follow all applicable OSHA requirements for drilling, silica dust control and personal protective equipment.
Get a Quote
Call 954-972-9787 or toll free 1-888-744-0442 and a salesperson will help you match the product to the job.
Construction & Electrical Products Inc. 1800 NW 15th Ave #155 Pompano Beach, FL 33069 Phone: 954-972-9787 · Toll free: 1-888-744-0442 Email: sales@constructionandelectrical.com Hours: Monday through Friday, 8:30 a.m. to 4:00 p.m. Closed Saturday and Sunday. No minimum order. Same-day shipping on most items. Drop shipment to the job site available. Certificates of Compliance and Mill Test Reports on request.